[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891237":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891237,577,1,"单选题","当拟建工程中有设备、管道冬雨季施工，有易燃易爆、有害环境施工，或设备、管道焊接质量要求较高时，措施项目可列项为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设备.管道焊接保护措施",false,{"key":16,"text":17,"correct":14},"B","压力容器和高压管道的检验",{"key":19,"text":20,"correct":21},"C","设备.管道施工的安全防冻和焊接保护",true,{"key":23,"text":24,"correct":14},"D","管道安装充气保护","本题考查的是安装工程措施项目清单。当拟建工程中有设备、管道冬雨季施工，有易燃易爆、有害环境施工，或设备、管道焊接质量要求较高时，措施项目可列项为“设备、管道施工的安全防冻和焊接保护”。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]