[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891223":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891223,577,1,"单选题","根据《通用安装工程工程量计算规范》（GB50856－2013），给水和采暖管道工程量计算时正确的为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","法兰阀门安装不包括法兰连接",false,{"key":16,"text":17,"correct":14},"B","阀门安装仅包括一侧法兰连接",{"key":19,"text":20,"correct":21},"C","法兰的计量单位为“副”或“片”",true,{"key":23,"text":24,"correct":14},"D","减压器规格按低压侧管道规格描述","本题考查的是给排水、采暖、燃气工程计量及应用。法兰阀门安装包括法兰连接，不得另计。阀门安装如仅为一侧法兰连接时，应在项目特征中描述。塑料阀门连接形式需注明热熔连接、粘接、热风焊接等方式。减压器规格按高压侧管道规格描述。法兰的计量单位为“副”或“片”。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]