[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891213":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},891213,577,1,"单选题","第十册《给排水、采暖、燃气工程》中规定，在洞库、暗室，已封闭的管道间（井）、地沟、吊顶内安装的项目，人工、机械乘以系数（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1.1",false,{"key":16,"text":17,"correct":18},"B","1.2",true,{"key":20,"text":21,"correct":14},"C","1.02",{"key":23,"text":24,"correct":14},"D","1.22","本题考查的是《2012安装预算定额》第十册《给排水、采暖、燃气工程》。在洞库、暗室，已封闭的管道间（井）、地沟、吊顶内安装的项目，人工、机械乘以系数1.2。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]