[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891184":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},891184,577,1,"单选题","在室内排水系统的排出管施工中，隐蔽前必须做（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","水压试验",false,{"key":16,"text":17,"correct":14},"B","气压试验",{"key":19,"text":20,"correct":14},"C","渗漏试验",{"key":22,"text":23,"correct":24},"D","灌水试验",true,"排出管在隐蔽前必须做灌水试验，其灌水高度应不低于底层卫生器具的上边缘或底层地面的高度。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]