[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891136":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},891136,577,1,"单选题","根据2017电气设备安装工程预算定额，下列说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","脚手架搭拆费按定额人工费的5%计算，其中费用中人工费占35%",false,{"key":16,"text":17,"correct":18},"B","操作高度除各章节另有规定者外，均按3m以下编制",true,{"key":20,"text":21,"correct":14},"C","建筑物层数大于6层应计算高层建筑增加费",{"key":23,"text":24,"correct":14},"D","定额不包括安装所用螺栓","本题考查的是建筑电气工程定额应用。操作高度除各章节另有规定者外，均按5m以下编制；当操作高度超过5m时，按相应规定执行。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]