[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891135,577,1,"单选题","根据2017电气设备安装工程预算定额，滑触线及支架安装高度定额是按10m以下编制的，若实际安装髙度超过此高度时，其超过部分的人工工日乘以系数（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1.5",false,{"key":16,"text":17,"correct":14},"B","1.25",{"key":19,"text":20,"correct":21},"C","1.2",true,{"key":23,"text":24,"correct":14},"D","1.15","本题考查的是建筑电气工程定额应用。滑触线及支架安装高度，定额是按10m以下编制的，若实际安装髙度超过此高度时，其超过部分的人工工日乘以系数1.2。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]