[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891117,577,1,"单选题","关于建筑电气工程安装时的预埋工作，不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","电气埋地保护管需在土建铺设地坪时预先敷设好",false,{"key":16,"text":17,"correct":14},"B","固定配电箱需在土建砌墙时同时埋设",{"key":19,"text":20,"correct":21},"C","避雷带的支座需在土建砌墙完成后埋设",true,{"key":23,"text":24,"correct":14},"D","进行预埋工作时，应注意不要破坏建筑物的结构强度和损坏建筑物的外观","本题考查的是建筑电气工程安装。预埋工作的特点是时间性强，需与土建施工交叉配合进行，并应密切配合主体工程的施工进度。隐蔽工程的施工，如电气埋地保护管等，需在土建铺设地坪时预先敷设好；一些固定支撑的预埋，如固定配电箱、避雷带的支座等，需在土建砌墙时同时埋设。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]