[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891091":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},891091,577,1,"单选题","建设工程投标限价反映的是（ ），其费用包括：分部分项工程费、措施项目费、其他项目费、规费和税金五部分。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程费用",false,{"key":16,"text":17,"correct":18},"B","单位工程费用",true,{"key":20,"text":21,"correct":14},"C","单项工程费用",{"key":23,"text":24,"correct":14},"D","建设项目","",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]