[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891076":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},891076,577,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013）。关于其他项目清单的编制和计价，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额由招标人在工程量清单中暂定",true,{"key":16,"text":17,"correct":18},"B","暂列金额包括暂不能确定价格的材料暂定价",false,{"key":20,"text":21,"correct":18},"C","专业工程暂估价中包括规费和税金",{"key":23,"text":24,"correct":18},"D","计日工单价中不包括企业管理费和利润","估价包括暂不能确定价格的材料暂定价，B错误；专业工程暂估价不包括规费和税金，C错误；计日工单价包含企业管理费和利润，D错误。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]