[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},891020,577,1,"单选题","下列关于通风空调系统泵的试运转说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","泵的试运转应在各独立的附属系统试运转正常后进行",false,{"key":16,"text":17,"correct":18},"B","泵在设计负荷下连续运转不应小于1h",true,{"key":20,"text":21,"correct":14},"C","运转中不应有异常的声音",{"key":23,"text":24,"correct":14},"D","滚动轴承的温度不应高于75℃","本题考查的是通风与空调工程施工技术。泵在设计负荷下连续运转不应小于2h。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]