[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-891010":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},891010,577,1,"单选题","按编制对象不同，施工组织设计的三个层次是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单位工程组织总设计、单项工程施工组织设计和施工方案",false,{"key":16,"text":17,"correct":14},"B","施工组织总设计、单项工程施工组织设计和施工进度计划",{"key":19,"text":20,"correct":21},"C","施工组织总设计、单位工程施工组织设计和施工方案",true,{"key":23,"text":24,"correct":14},"D","指导性施工组织设计、实施性施工组织设计和施工方案","按编制对象不同，施工组织设计包括三个层次，即：施工组织总设计、单位工程施工组织设计和施工方案。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]