[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},890943,577,1,"单选题","下列关于施工组织设计的说法中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已经批准的施工组织设计未经审批施工方不得擅自修改",false,{"key":16,"text":17,"correct":18},"B","扩大施工用地需经过批准后方可修改",true,{"key":20,"text":21,"correct":14},"C","施工组织设计是施工现场各级技术交底的主要内容之一",{"key":23,"text":24,"correct":14},"D","增加临时建筑面积需重新履行原审批手续","本题主要考查的是施工组织设计。施工组织设计一经批准，施工单位和工程相关单位应认真贯彻执行，未经审批不得修改，原则的重大变更须履行原审批手续。凡涉及增加临时建筑面积、提高建筑标准、扩大施工用地、修改重大施工方案、降低质量目标等主要原则的重大变更，须履行原审批手续。B错误，扩大施工用地属于原则重大变更，不能修改需要重新履行原审批手续。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]