[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},890942,577,1,"单选题","施工组织设计的编制需要遵循一定的顺序原则，编制资源需要量计划后紧接着应做的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制施工总进度计划",false,{"key":16,"text":17,"correct":14},"B","确定施工部署",{"key":19,"text":20,"correct":21},"C","制定施工临时设施计划",true,{"key":23,"text":24,"correct":14},"D","布置施工总平面图","本题主要考查的是施工组织设计。编制资源需要量计划后需要制定施工临时设施计划。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]