[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890820":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},890820,577,1,"单选题","承包人向发包人提交竣工结算款支付申请不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工结算合同价款总额",false,{"key":16,"text":17,"correct":18},"B","预计应支付的竣工结算款金额",true,{"key":20,"text":21,"correct":14},"C","累计已实际支付的合同价款",{"key":23,"text":24,"correct":14},"D","应扣留的质量保证金","承包人应根据办理的竣工结算文件，向发包人提交竣工结算款支付申请。该申请应包括下列内容： （1）竣工结算合同价款总额。 （2）累计已实际支付的合同价款。 （3）应扣留的质量保证金。 （4）实际应支付的竣工结算款金额。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]