[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890798":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},890798,577,1,"单选题","发包人应在工程开工后的28d内预付不低于当年施工进度计划的安全文明施工费总额的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":14},"B","40%",{"key":19,"text":20,"correct":21},"C","60%",true,{"key":23,"text":24,"correct":14},"D","90%","安全文明施工费的支付。发包人应在工程开工后的28d内预付不低于当年施工进度计划的安全文明施工费总额的60%，其余部分按照提前安排的原则进行分解，与进度款同期支付。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]