[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},890795,577,1,"单选题","进度款的支付比例最高不超过（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","60%",false,{"key":16,"text":17,"correct":14},"B","70%",{"key":19,"text":20,"correct":14},"C","80%",{"key":22,"text":23,"correct":24},"D","90%",true,"",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]