[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890753":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},890753,577,1,"单选题","采暖主干管的工程量计算规则中，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","采暖系统干管应包括供水干管与回水干管两部分",false,{"key":16,"text":17,"correct":14},"B","计算时应从底层供暖管道入口处开始，沿着干管走向，直到建筑内部各干管末端为止",{"key":19,"text":20,"correct":21},"C","计算时应先从小管径开始，逐步计算至大管径",true,{"key":23,"text":24,"correct":14},"D","主干立管应按照管道系统轴测图中所注标高计算","A项，干管应包括供水干管与回水干管两部分。B项，计算时应从底层供暖管道入口处（室内、外以入口阀门或建筑物外墙皮1.50m为界）开始，沿着干管走向，直到建筑内部各干管末端为止，同时还应包括供水干管最高点自动排气阀接出的放气管。C项，计算时应先从大管径开始，逐步计算至小管径，此时应特别注意干管管径的变化位置（即大管径与小管径的分界线，应在小管径前的第一个分流点处），并应掌握管道的安装位置及尺寸。D项，主干立管应按管道系统轴测图中所注标高计算。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]