[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890750":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},890750,577,1,"单选题","依据《通用安装工程工程量计算规范》（GB 50856-2013）的规定，利用基础钢筋作接地极，应执行的清单项目是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","接地极项目",false,{"key":16,"text":17,"correct":14},"B","接地母线项目",{"key":19,"text":20,"correct":14},"C","基础钢筋项目",{"key":22,"text":23,"correct":24},"D","均压环项目",true,"利用桩基础作接地极，应描述桩台下桩的根数，每桩台下需焊接柱筋根数，其工程量按柱引下线计算；利用基础钢筋作接地极按均压环项目编码列项。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]