[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},890722,577,1,"单选题","变压器试运行时，一般应先进行（ ）次空载全电压冲击。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","6","变压器试运行往往采用全电压冲击合闸的方法，一般应进行5次空载全电压冲击合闸，无异常情况，即可空载运行24h，正常后，再带负荷运行24h以上，无任何异常情况时，则认为试运行合格。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]