[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},890699,577,1,"单选题","在通风空调系统的无生产负荷联合试运转中，测试和调整内容除了需进行通风机风量、风压及转速测定外，还包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","通风机试运转",false,{"key":16,"text":17,"correct":14},"B","水泵试运转",{"key":19,"text":20,"correct":14},"C","制冷机试运转",{"key":22,"text":23,"correct":24},"D","通风机、制冷机、空调器的噪声测定",true,"通风（空调）系统无生产负荷联合试运转测定与调整的内容如下：①通风机风量、风压及转速测定，通风（空调）设备风量、余压与风机转速测定；②系统与风口的风量测定与调整；③通风机、制冷机、空调器的噪声测定；④制冷系统运行的压力、温度、流量等各项技术数据应符合有关技术文件的规定；⑤防排烟系统正压送风前室静压的检测；⑥空气净化系统，应进行高效过滤器的检漏和室内洁净度级别的测定；⑦空调系统带冷、热源的正常联合试运转应大于8h，当竣工季节条件与设计条件相差较大时，仅做不带冷、热源的试运转。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]