[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},890669,577,1,"单选题","煤气发生设备一般按（ ）的原则进行安装。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先下后上",true,{"key":16,"text":17,"correct":18},"B","先里后外",false,{"key":20,"text":21,"correct":18},"C","先易后难",{"key":23,"text":24,"correct":18},"D","先上后下","煤气发生设备安装时，一般按先下后上的原则安装。安装顺序为：①底部支撑的安装；②轴承圈安装；③灰盘安装；④水夹套的安装；⑤加煤机的安装；⑥爬车轨道的安装；⑦大、小灰刀安装；⑧清灰机的安装。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]