[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890568":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},890568,577,1,"单选题","下列选项中，不属于施工组织设计的主要施工管理计划的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度管理计划",false,{"key":16,"text":17,"correct":14},"B","质量管理计划",{"key":19,"text":20,"correct":21},"C","责任管理计划",true,{"key":23,"text":24,"correct":14},"D","安全管理计划","施工组织设计的主要施工管理计划应包括进度管理计划、质量管理计划、安全管理计划、环境管理计划、成本管理计划以及其他管理计划等内容。各项管理计划的制订应根据项目的特点有所侧重。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]