[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},890566,577,1,"单选题","单位工程施工平面图设计，一般按（ ）的比例绘制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1︰400～1︰200",false,{"key":16,"text":17,"correct":14},"B","1︰500～1︰100",{"key":19,"text":20,"correct":14},"C","1︰300～1︰200",{"key":22,"text":23,"correct":24},"D","1︰500～1︰200",true,"单位工程施工现场平面图是施工时施工现场的平面规划与布置图。它是单位工程施工组织设计的重要组成部分。一张好的施工平面布置图将会提高施工效率，保证施工进度计划有条不紊地顺利实施。反之，如果施工平面图设计不周或施工现场管理不当，都将导致施工现场的混乱，直接影响施工进度、劳动生产率和工程成本。单位工程施工平面图设计的主要依据是单位工程的施工方案和施工进度计划，一般按1︰500～1︰200的比例绘制。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]