[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},890559,577,1,"单选题","计划工期等于计算工期的双代号网络计划中，关于关键节点特点的说法，正确的是( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","相邻关键节点之间的工作一定是关键工作",false,{"key":16,"text":17,"correct":18},"B","以关键节点为完成节点的工作总时差和自由时差相等",true,{"key":20,"text":21,"correct":14},"C","关键节点连成的线路一定是关键线路",{"key":23,"text":24,"correct":14},"D","两个关键节点之间的线路一定是关键线路","",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]