[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890558":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},890558,577,1,"单选题","流水施工中某施工过程(专业工作队)在单位时间内所完成的工程量称为( )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","流水段",false,{"key":16,"text":17,"correct":18},"B","流水强度",true,{"key":20,"text":21,"correct":14},"C","流水节拍",{"key":23,"text":24,"correct":14},"D","流水步距","",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]