[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890523":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},890523,577,1,"单选题","某工作现场要求起重机吊装能力为 3～100t,臂长 40～80m,使用地点固定、使用周期较长且较经济。一般为单机作业，也可双机抬吊。应选用的吊装方法为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","液压提升法",false,{"key":16,"text":17,"correct":14},"B","桅杆系统吊装",{"key":19,"text":20,"correct":21},"C","塔式起重机吊装",true,{"key":23,"text":24,"correct":14},"D","桥式起重机吊装","本题考查塔式起重机吊装。起重吊装能力为 3～100t，臂长在 40～80m，常用在使用地点固定、使用周期较长的场合，较经济。一般为单机作业，也可双机抬吊。故C选项正确。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]