[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890471":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},890471,577,1,"单选题","下列关于吹扫与清洗的表述，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管道吹扫与清洗前，以焊接形式连接的阀门、仪表等部件，应暂时拆除以模拟件或临时短管替代，待管道吹洗合格后再重新复位",true,{"key":16,"text":17,"correct":18},"B","蒸汽吹扫前，应先进行暖管，并及时疏水",false,{"key":20,"text":21,"correct":18},"C","油清洗合格的管道，应采取封闭或充氮保护措施",{"key":23,"text":24,"correct":18},"D","蒸汽吹扫应按加热、冷却、再加热的顺序循环进行","A项，管道吹扫与清洗前，应将系统内的仪表、孔板、节流阀、调节阀、电磁阀、安全阀、止回阀等管道组件暂时拆除，以模拟件或临时短管替代，待管道吹洗合格后再重新复位。对以焊接形式连接的上述阀门、仪表等部件，应采取流经旁路或卸掉阀头及阀座加保护套等保护措施后再进行吹扫与清洗。B项，蒸汽吹扫前，应先进行暖管，并及时疏水。暖管时，应检查管道的热位移，当有异常时，应及时进行处理。D项，蒸汽吹扫应按加热、冷却、再加热的顺序循环进行。吹扫时宜采取每次吹扫一根，轮流吹扫的方法。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]