[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},890470,577,1,"单选题","某DN100的输送常温液体的管道，在安装完毕后应做的后续辅助工作为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","气压试验，蒸汽吹扫",false,{"key":16,"text":17,"correct":14},"B","气压试验，压缩空气吹扫",{"key":19,"text":20,"correct":21},"C","水压试验，水清洗",true,{"key":23,"text":24,"correct":14},"D","水压试验，压缩空气吹扫","管道系统安装后，在压力试验合格后，应进行吹扫与清洗。管道吹扫与清洗方法的选用，应根据管道的使用要求、工作介质、系统回路、现场条件及管道内表面的脏污程度确定。除设计文件有特殊要求的管道外，一般DN＜600mm的液体管道，宜采用水冲洗。管道的压力试验一般以液体为试验介质。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]