[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890460":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},890460,577,1,"单选题","热力管道在采用蒸汽吹扫前应进行的工作为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","酸洗、钝化",false,{"key":16,"text":17,"correct":14},"B","空气吹扫与清洗",{"key":19,"text":20,"correct":14},"C","水清洗与吹干",{"key":22,"text":23,"correct":24},"D","暖管与疏水",true,"管道系统安装后，在压力试验合格后，应进行吹扫与清洗。当采用蒸汽吹扫法时应注意以下几点：①蒸汽吹扫前，管道系统的绝热工程应已完成。②蒸汽吹扫应以大流量蒸汽进行吹扫，流速不应小于30m\u002Fs。③蒸汽吹扫前，应先进行暖管，并及时疏水。暖管时，应检查管道的热位移，当有异常时，应及时进行处理。④蒸汽吹扫应按加热、冷却、再加热的顺序循环进行。吹扫时宜采取每次吹扫一根和轮流吹扫的方法。⑤经蒸汽吹扫后，应对吹扫靶板进行检验，靶板无脏物为合格。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]