[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890436":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},890436,577,1,"单选题","某工作现场要求起重机吊装能力为3～100t，臂长40～80m，使用地点固定、使用周期较长且较经济。一般为单机作业，也可双机抬吊，应选用的吊装方法为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","液压提升法",false,{"key":16,"text":17,"correct":14},"B","桅杆系统吊装",{"key":19,"text":20,"correct":21},"C","塔式起重机吊装",true,{"key":23,"text":24,"correct":14},"D","桥式起重机吊装","C项，塔式起重机吊装的起重吊装能力为3～100t，臂长在40～80m，常用在使用地点固定、使用周期较长的场合，较经济。一般为单机作业，也可双机抬吊。A项，液压提升，目前多采用“钢绞线悬挂承重、液压提升千斤顶集群、计算机控制同步”方法整体提升（滑移）大型设备与构件。B项，主要适用于某些特重、特高和场地受到特殊限制的设备、构件吊装。D项，桥式起重机吊装，起重能力为3～1000t，跨度在3～150m，多为仓库、厂房、车间内使用，一般为单机作业，也可双机抬吊。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]