[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890427":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},890427,577,1,"单选题","除直接埋地管道外，以下是给排水管道安装中最靠前的工序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开挖地沟",false,{"key":16,"text":17,"correct":14},"B","材料准备和材料预处理",{"key":19,"text":20,"correct":21},"C","管道支架制作与安装",true,{"key":23,"text":24,"correct":14},"D","设备安装","管道安装工程一般施工程序：施工准备→测量定位→支架制作安装→管道预制安装→仪表安装→试压清洗→防腐保温→调试及试运行→交工验收。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]