[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890369":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},890369,577,1,"单选题","生活给水系统在交付使用之前必须进行冲洗和消毒，以下作法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","试压合格后，利用系统内存水进行冲洗，再进行消毒",false,{"key":16,"text":17,"correct":18},"B","冲洗顺序是先室外、后室内；先地下、后地上",true,{"key":20,"text":21,"correct":14},"C","室内部分的冲洗顺序应为配水管、配水干管、配水支管",{"key":23,"text":24,"correct":14},"D","消毒用水应在管道中停留12h","冲洗顺序应先室外，后室内；先地下，后地上。室内部分的冲洗应按配水干管、配水管、配水支管的顺序进行。饮用水管道在使用前用每升水中含20～30mg游离氯的水灌满管道进行消毒，水在管道中停留24h以上。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]