[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-890356":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},890356,577,1,"单选题","污水排出管安装完毕后，在隐蔽之前必须做（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水压试验",false,{"key":16,"text":17,"correct":18},"B","灌水试验",true,{"key":20,"text":21,"correct":14},"C","渗透试验",{"key":23,"text":24,"correct":14},"D","通球试验","排出管在隐蔽前必须做灌水试验，其灌水高度应不低于底层卫生器具的上边缘或底层地面的高度。",{"id":6,"name":27,"category":28,"favorite":29},"[安装工程]建设工程计量与计价实务","建筑工程",0]