[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-889971":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},889971,574,2,"多选题","2014-109．根据《中华人民共和国环境影响评价法》，应当组织环境影响后评价的情形包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","某输油管线项目跨越两省区并存在重大环境风险",true,{"key":16,"text":17,"correct":18},"B","某化工厂环境影响评价文件经批准后，采用的生产工艺发生重大变动",false,{"key":20,"text":21,"correct":14},"C","某公路建设项目的选线发生较大变化，经由自然保护区实验区的长度有所增加",{"key":23,"text":24,"correct":14},"D","某电厂运行过程中锅炉除尘工艺发生变化，致使烟尘排放强度与环境影响预测情况相比有较大变化","ACD","",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价相关法律法规","建筑工程",0]