[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-889497":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},889497,574,2,"多选题","根据《关于进一步加强水电建设环境保护工作的通知》，下列水电工程中，属于应纳入“三通一平”工程开展环境影响评价的有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","围堰工程",false,{"key":16,"text":17,"correct":14},"B","河床内导流工程",{"key":19,"text":20,"correct":21},"C","筹建及准备期相关工程",true,{"key":23,"text":24,"correct":21},"D","水生生态保护的相关工程措施","CD","根据《关于进一步加强水电建设环境保护工作的通知》第三条规定，要规范水电项目“三通一平”工程环境影响评价工作。水电项目筹建及准备期相关工程应作为一个整体项目纳入“三通一平”工程开展环境影响评价。水生生态保护的相关措施应列为水电项目筹建及准备期工作内容；围堰工程（包括分期围堰）和河床内导流工程作为主体工程内容，不纳入“三通一平”工程范围。在水电建设项目环境影响评价中要有“三通一平”工程环境影响回顾性评价内容。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价相关法律法规","建筑工程",0]