[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-889449":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},889449,574,2,"多选题","依据《关于进一步加强环境影响评价管理防范环境风险的通知》，下列关于建设项目环境风险评价的要求，说法错误的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对改、扩建相关建设项目，对现有工程可能存在的环境风险隐患，应提出相应的补救或完善措施，并纳入改、扩建项目“三同时”验收内容",false,{"key":16,"text":17,"correct":18},"B","相关建设项目的环境影响评价文件经批准后，环境风险防范设施发生重大变动的，建设单位应按《中华人民共和国环境影响评价法》要求重新审核",true,{"key":20,"text":21,"correct":18},"C","对存在较大环境风险隐患的建设项目环境影响评价文件，应提出环境影响后评价的要求",{"key":23,"text":24,"correct":14},"D","建设项目的环境风险防范设施和应急措施是企业环境风险防范与应急管理体系的组成部分参考答案","BC","B项，相关建设项目的环境影响评价文件经批准后，环境风险防范设施发生重大变动的，建设单位应按《中华人民共和国环境影响评价法》要求重新办理报批手续。C项，环保部门在相关建设项目环境影响评价文件审批中，对存在较大环境风险隐患的，应提出环境影响后评价的要求。",{"id":6,"name":28,"category":29,"favorite":30},"环境影响评价相关法律法规","建筑工程",0]