[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-889432":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},889432,574,2,"多选题","对已经批准的规划，下列（ ）情况规划编制机关应当依照《规划环境影响评价条例》的规定重新或者补充进行环境影响评价。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","实施范围有重大调整",true,{"key":16,"text":17,"correct":14},"B","适用期限进行重大修订",{"key":19,"text":20,"correct":14},"C","规划规模进行重大调整",{"key":22,"text":23,"correct":14},"D","结构和布局进行重大修订","ABCD","按照《规划环境影响评价条例》规定，将规划环评结论作为规划所包含建设项目环评的重要依据，建立规划环评与项目环评的联动机制。未进行环境影响评价的规划所包含的建设项目，不予受理其环境影响评价文件。已经批准的规划在实施范围、适用期限、规模、结构和布局等方面进行重大调整或者修订的，应当重新或者补充进行环境影响评价，未开展环评的，不予受理其规划中建设项目的环境影响评价文件。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]