[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-889087":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},889087,574,1,"单选题","根据《中华人民共和国海洋环境保护法》关于海洋工程建设项目污染损害海洋环境的防治，下列说法错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","海洋工程建设项目单位应当对海洋环境进行科学调查，编制海洋环境影响报告书(表)，并在建设项目开工前，报海洋行政主管部门审查批准。",false,{"key":16,"text":17,"correct":14},"B","海洋行政主管部门在批准海洋环境影响报告书(表)之前，必须征求海事、渔业行政主管部门和军队环境保护部门门的意见。",{"key":19,"text":20,"correct":14},"C","拆除或者闲置环境保护设施，必须事先征得海洋行政主管部门门的同意。",{"key":22,"text":23,"correct":24},"D","海洋石油钻井船、钻井平台和采油平台的含油污水和油性混合物必须予以回收",true,"",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]