[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-888846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},888846,574,1,"单选题","2013-111．根据《中华人民共和国环评影响评价法》，关于环境影响后评价的规定，下列说法中，错误的有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在项目建设过程中产生不符合经审批的环境影响评价文件的情形的，建设单位应当组织环境影响的后评价，采取改进措施",false,{"key":16,"text":17,"correct":14},"B","在项目运行过程中产生不符合经审批的环境影响评价文件的情形的，建设单位应当组织环境影响的后评价，采取改进措施",{"key":19,"text":20,"correct":21},"C","在项目关闭过程中产生不符合经审批的环境影响评价文件的情形的，建设单位应当组织环境的后评价，采取改进措施",true,{"key":23,"text":24,"correct":14},"D","在项目建设过程中产生不符合经审批的环境影响评价文件情形的，原环境影响评价文件审批部门可以责成建设单位进行环境影响的后评价，采取改进措施","",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]