[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-888833":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},888833,574,1,"单选题","某高速公路建设项目设计阶段发生重大变动，根据《高速公路建设项目重大变动清单（试行）》，属于重大变动的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计车速增加20%",true,{"key":16,"text":17,"correct":18},"B","线路长度增加20%",false,{"key":20,"text":21,"correct":18},"C","线路横向位移超出200米长度累计达到原线路长度的20%",{"key":23,"text":24,"correct":18},"D","项目变动导致新增声环境敏感点数量累计达到原敏感点数量的20%","",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]