[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-888807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},888807,574,1,"单选题","2018-22、某工业建设项目环境影响评价文件于2010 年通过省级环境保护主管部门审批建设单位于2016 年方决定开工建设该建设项目供水方案发生重变动，该建设项目环境影响评价文件审批权限已调整为市级环境保护主管部门，根据《中华人民共和国环境影响评价法》，关于该建设项目环境影响评价管理的说法，正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","应纳入竣工环境保护验收管理",false,{"key":16,"text":17,"correct":14},"B","应当重新报批，该建设项目的环境影响评价文件",{"key":19,"text":20,"correct":21},"C","该建设项目的环境影响评价文件应当报省级环境保护行政主管部门重新审核",true,{"key":23,"text":24,"correct":14},"D","该建设项目的环境影晌评价文件应当报市级环境保护主管部重新审核","",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]