[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-888312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},888312,574,1,"单选题","依据《中华人民共和国森林法》，进行勘查、开采矿藏和各项建设工程（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不得占用林地",false,{"key":16,"text":17,"correct":18},"B","应当不占或少占林地",true,{"key":20,"text":21,"correct":14},"C","必须占用林地的，应当经县级以上人民政府批准",{"key":23,"text":24,"correct":14},"D","已占用林地的，应当由用地单位安排植树造林恢复植被","根据《中华人民共和国森林法》第十八条规定，进行勘查、开采矿藏和各项建设工程，应当不占或者少占林地；必须占用或者征用林地的，经县级以上人民政府林业主管部门审核同意后，依照有关土地管理的法律、行政法规办理建设用地审批手续，并由用地单位依照国务院有关规定缴纳森林植被恢复费。森林植被恢复费专款专用，由林业主管部门依照有关规定统一安排植树造林，恢复森林植被，植树造林面积不得少于因占用、征用林地而减少的森林植被面积。上级林业主管部门应当定期督促、检查下级林业主管部门组织植树造林、恢复森林植被的情况。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]