[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887963":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},887963,574,1,"单选题","根据《中华人民共和国环境影响评价法》，审批部门应当自收到环境影响报告书之日起（ ）日内，作出审批决定并书面通知建设单位。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","30",{"key":19,"text":20,"correct":21},"C","60",true,{"key":23,"text":24,"correct":14},"D","45","根据《中华人民共和国环境影响评价法》第二十二条规定，建设项目的环境影响报告书、报告表，由建设单位按照国务院的规定报有审批权的环境保护行政主管部门审批；海洋工程建设项目的海洋环境影响报告书的审批，依照《中华人民共和国海洋环境保护法》的规定办理。审批部门应当自收到环境影响报告书之日起六十日内，收到环境影响报告表之日起三十日内，收到环境影响登记表之日起十五日内，分别作出审批决定并书面通知建设单位。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]