[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},887946,574,1,"单选题","根据《中华人民共和国环境影响评价法》，在项目建设、运行过程中产生不符合经审批的环境影响评价文件的情形的，建设单位应当组织环境影响的后评价，采取改进措施并（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","报原环境影响评价文件审批部门和建设项目审批部门审批",false,{"key":16,"text":17,"correct":18},"B","报原环境影响评价文件审批部门和建设项目审批部门备案",true,{"key":20,"text":21,"correct":14},"C","报具有该项目环境影响评价文件审批权限部门和建设项目审批部门审批",{"key":23,"text":24,"correct":14},"D","报具有该项目环境影响评价文件审批权限部门和建设项目审批部门备案","根据《中华人民共和国环境影响评价法》第二十七条规定，在项目建设、运行过程中产生不符合经审批的环境影响评价文件的情形的，建设单位应当组织环境影响的后评价，采取改进措施，并报原环境影响评价文件审批部门和建设项目审批部门备案。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]