[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},887940,574,1,"单选题","某机械加工企业运行过程中产生了不符合经审批的环境影响报告书情形，依据《中华人民共和国环境影响评价法》，该企业应当采取的正确做法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","立即停止生产",false,{"key":16,"text":17,"correct":14},"B","重新编制该建设项目的环境影响报告并报环境保护行政主管部门审批",{"key":19,"text":20,"correct":14},"C","组织环境影响的后评价，采取改进措施，并报原环境影响报告书审批部门备案",{"key":22,"text":23,"correct":24},"D","组织环境影响的后评价，采取改进措施，并报原环境影响报告书审批部门和建设项目审批部门备案",true,"《中华人民共和国环境影响评价法》第二十七条规定，在项目建设、运行过程中产生不符合经审批的环境影响评价文件的情形的，建设单位应当组织环境影响的后评价，采取改进措施，并报原环境影响评价文件审批部门和建设项目审批部门备案；原环境影响评价文件审批部门也可以责成建设单位进行环境影响的后评价，采取改进措施。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]