[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},887920,574,1,"单选题","对需重新审核的建设项目的环境影响评价文件，原审批机关应当自收到建设项目环境影响评价文件之日起10日内，将审核意见（ ）建设单位。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","口头通知",false,{"key":16,"text":17,"correct":14},"B","电话通知",{"key":19,"text":20,"correct":21},"C","书面通知",true,{"key":23,"text":24,"correct":14},"D","邮件通知","《中华人民共和国环境影响评价法》第二十四条规定，建设项目的环境影响评价文件经批准后，建设项目的性质、规模、地点、采用的生产工艺或者防治污染、防止生态破坏的措施发生重大变动的，建设单位应当重新报批建设项目的环境影响评价文件。建设项目的环境影响评价文件自批准之日起超过五年，方决定该项目开工建设的，其环境影响评价文件应当报原审批部门重新审核；原审批部门应当自收到建设项目环境影响评价文件之日起十日内，将审核意见书面通知建设单位。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]