[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},887914,574,1,"单选题","依据《中华人民共和国环境影响评价法》，建设项目环境影响报告书应当在（ ）报批。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开工建设前",true,{"key":16,"text":17,"correct":18},"B","初步设计阶段",false,{"key":20,"text":21,"correct":18},"C","可行性研究完成后",{"key":23,"text":24,"correct":18},"D","初步设计完成前","《建设项目环境保护管理条例》第九条规定，依法应当编制环境影响报告书、环境影响报告表的建设项目，建设单位应当在开工建设前将环境影响报告书、环境影响报告表报有审批权的环境保护行政主管部门审批；建设项目的环境影响评价文件未依法经审批部门审查或者审查后未予批准的，建设单位不得开工建设。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]