[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887913":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},887913,574,1,"单选题","依据《建设项目环境影响评价文件审批程序规定》，下列建设项目中，省级以下环境保护部门无权审批其环境影响评价文件的是（ ）建设项目。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","化工",false,{"key":16,"text":17,"correct":14},"B","造纸",{"key":19,"text":20,"correct":14},"C","印染",{"key":22,"text":23,"correct":24},"D","电石",true,"根据《建设项目环境影响评价文件分级审批规定》（中华人民共和国环境保护部令第5号）规定，有色金属冶炼及矿山开发、钢铁加工、电石、铁合金、焦炭、垃圾焚烧及发电、制浆等对环境可能造成重大影响的建设项目环境影响评价文件由省级环境保护部门负责审批。化工、造纸、电镀、印染、酿造、味精、柠檬酸、酶制剂、酵母等污染较重的建设项目环境影响评价文件由省级或地级市环境保护部门负责审批。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]