[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887912":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},887912,574,1,"单选题","依据《建设项目环境保护管理条例》，对于不需要进行可行性研究的建设项目，建设单位报建设项目环境影响评价文件的时间应当是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设项目开工后",false,{"key":16,"text":17,"correct":18},"B","建设项目开工前",true,{"key":20,"text":21,"correct":14},"C","建设项目竣工前",{"key":23,"text":24,"correct":14},"D","建设项目竣工后","《建设项目环境保护管理条例》第九条规定，按照国家有关规定，依法应当编制环境影响报告书、环境影响报告表的建设项目，建设单位应当在开工建设前将环境影响报告书、环境影响报告表报有审批权的环境保护行政主管部门审批；建设项目的环境影响评价文件未依法经审批部门审查或者审查后未予批准的，建设单位不得开工建设。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]