[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-887902":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},887902,574,1,"单选题","根据《建设项目环境保护管理条例》，环境保护行政主管部门审批环境影响报告书，自收到环境影响报告书之日起（ ）内，作出审批决定并书面通知建设单位。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","15日",false,{"key":16,"text":17,"correct":14},"B","30日",{"key":19,"text":20,"correct":21},"C","60日",true,{"key":23,"text":24,"correct":14},"D","90日","根据《建设项目环境保护管理务例》第九条规定，生态环境主管部门审批环境影响报告书、环境影响报告表，应当重点审查建设项目的环境可行性、环境影响分析预测评估的可靠性、环境保护措施的有效性、环境影响评价结论的科学性等，并分别自收到环境影响报告书之日起60日内、收到环境影响报告表之日起30日内，作出审批决定并书面通知建设单位。",{"id":6,"name":27,"category":28,"favorite":29},"环境影响评价相关法律法规","建筑工程",0]